No.
|
Construction Company
|
Project Name
|
Project Content
|
Weight/Ton
|
|
1
|
Jiangsu Gaozi Power Generation Co., Ltd.
|
Project 2x600MW of Phase I
|
Steel structures for gas machine room and coal warehouse etc
|
5000
|
|
2
|
Zhejiang Yisheng Petrochemical Co., Ltd.
|
PTA Project with 530 thousand tons per year
|
Steel structures of main equipment
|
11200
|
|
3
|
National Power Changzhou Electricity Power Plant Project Phase I
|
Super-critical machine sets 2X600MW
|
Steel structures for gas machine room and coal warehouse etc
|
12850
|
|
4
|
Zhenjiang Power Generation Co., Ltd.
|
2*600MW
|
Channel bracket for one-off fans
|
400
|
|
5
|
Lift well 4x600MW and steel structure of lift well 58 by Ligang Electricity Power Plant
|
|
|
|
|
6
|
Qishuyan Electricity Power Plant
|
Qishuyan Electricity Power Plant
|
Steel structures for main workshops
|
2370
|
|
7
|
Qishuyan Electricity Power Plant
|
Remaining heat boiler 2x390MW
|
Crust steel structures
|
1000
|
|
8
|
Qishuyan Electricity Power Plant
|
Steel chimneys, stairs, pipeline brackets, platforms on the top of furnace and supports 7mx60m
|
Steel structure
|
1000
|
|
9
|
Jiangsu Huadian Yangzhou Power Generation Co., Ltd.
|
Smoke desulfurization absorbing tower Φ13m*26.2m
|
Heating generator sets for smoke desulfurization 2x300MW
|
700
|
|
10
|
Hunan Shimen Electricity Power Plant
|
Smoke desulfurization absorbing tower Φ11.46m*27.67m
|
Smoke desulfurization project 2x300MW
|
400
|
|
11
|
Degussa Special Chemical (China) Co., Ltd.
|
Polyester and colorant for multi-user base of Degussa (China)
|
Steel structures of tubes
|
1300
|
|
12
|
India Sagardighi Power Plant
|
Project of coal power plant 2x300MW
|
Main workshops (gas machine room & coal warehouse)
|
9000
|
|
13
|
Zhejiang Hualian Sanxin Petrochemical Co., Ltd.
|
PTA project Phase II
|
Steel structure of main equipment
|
3400
|
|
14
|
Zhejiang Yisheng Petrochemical Co., Ltd.
|
PTA reconstructed steel structure project 1 million tons per year
|
Steel structures
|
4400
|
|
15
|
Amarkantak (India) Power Plant
|
Smoke blowpipe 2x300MW
|
Steel structures of boilers
|
1500
|
|
16
|
Vietnam Coast Defence Power Plant
|
Firepower electricity generation project Phase I 2x300MW
|
Steel structures of main workshops
|
7000
|
|
17
|
Zibo Hongda Steel Co., Ltd.
|
3*220t/h
|
Steel structures of boilers
|
455
|
|
18
|
Jiangyin Thermal Power Plant
|
130 t/h
|
Steel structures of boilers
|
200
|
|
19
|
Shijiazhuang Hi-tech District Thermal Power Gas Corporation
|
240t/h
|
Steel structures of boilers
|
550
|
|
20
|
Huarun Power (Yixing) Co., Ltd. Thermal Power Project
|
260t/h
|
Steel structures of boilers
|
350
|
|
21
|
Shanxi Jinneng New Energy Sources Power Generation Co., Ltd.
|
220t/h
|
Steel structures of boilers
|
500
|
|
22
|
Jiangyin Xinyuan Power Generation Co., Ltd.
|
260 t/h
|
Steel structures of boilers
|
200
|
|
23
|
Benxi Beiying Steel (Group) Co., Ltd.
|
130 t/h
|
Steel structures of boilers
|
200
|
|
24
|
Anqiu Tiantian Thermal Power Co., Ltd.
|
75 t/h
|
Steel structures of boilers
|
100
|
|
25
|
Suzhou Suyuan Estate Investment Co., Ltd.
|
130 t/h
|
Steel structures of boilers
|
200
|
|
26
|
Wuxi Thermal Power Plant
|
130 t/h
|
Steel structures of boilers
|
200
|
|
27
|
Heilongjiang Dongchengfu Foods Corporation
|
35 t/h
|
Steel structures of boilers
|
100
|
|
28
|
Shanghai Yueyuan Machinery Co., Ltd.
|
220 t/h
|
Steel structures of boilers
|
3750
|
|
29
|
Jiaxing Jies Thermal Power Co., Ltd.
|
220 t/h
|
Steel structures of boilers
|
512
|
|
30
|
Zhangjiagang Hengdong Thermal Power Co., Ltd.
|
130 t/h
|
Steel structures of boilers
|
200
|
|
31
|
Suzhou Dongwu Thermal Power Co., Ltd.
|
130 t/h
|
Steel structures of boilers
|
200
|